What falls due

Since the AGM

Penchev 2 was extended in July

On 20 July 2026 the Penchev 2 loan, a facility of up to €2.0 million, was extended to 31 August 2027. The rate rose from 15% to 20%. €1,125,000 had been drawn. The table below is the position in the AGM presentation, dated 15 June 2026, before that notice.

31 Aug 2027

New maturity of Penchev 2

20%

Rate after the extension

€1,125,000

Drawn at the time of the notice

€18.3m

Combined on 1 Nov 2026, AGM basis

EPO Aheloy, 15 June 2026

LenderPrincipalMonthly interestRateDue1 Nov 2026Security
FIB, bank loan€7,655,000€35,628~5.5%October 2037€7,052,000First-priority mortgage on the property
Penchev Consult€7,400,000€100,43718.0%31 October 2026€7,900,00050% of the shares in EPO Aheloy
FIB, liquidity line€300,000€3,715~16.0%November 2026€0First-priority mortgage on the property
Total€15,355,000€139,780€14,952,000BSP owns 75% of EPO Aheloy

Figures are 100% of EPO Aheloy. BSP’s ownership is 75%.

Black Sea Property AS, 15 June 2026

LenderPrincipalMonthly interestRateDue1 Nov 2026Security
Penchev 2€1,125,000€14,06215.0%31 August 2026€2,210,000Pledge over EPOB shares
Shareholder loan no. 1€485,000€7,27518.0%30 November 2026€685,000Unsecured
Seller credit€500,000——None€500,000Unsecured
Total€2,110,000€21,337€3,395,000100% of the parent

The €2,210,000 shown for Penchev 2 on 1 November 2026 assumed the facility was fully drawn, extended by a year, and repaid by 31 August 2027. The line items of the two November columns sum to the combined figure in the presentation, €18,347,000.

AGM outlook

The order of work

01
Refinance the bridge loan

Bank refinancing of the Penchev facility, about €8 million, was the first priority for October 2026.

02
Cover the bank interest

After refinancing, the rent should carry the bank-loan cost.

03
Limit new equity

Further shareholder contributions were to be limited.

04
An exit at market

The sale process continues. The AGM was told it would not close before the loans expire.

05
Act 16 for building P

Official permission for use of building P was still open.

06
Other operating models

K and L, and the rent, were to be looked at for more revenue and EBITDA.

Debt table from the AGM presentation of 30 June 2026, prepared as at 15 June 2026. The extension of Penchev 2 is the Euronext notice of 20 July 2026.